Plan: Close the SRS Compliance Gap
Date: 2026-07-28 Source artifacts:
evidence/audit-2026-07-28.md— full SRS audit (this plan's baseline)evidence/post-fix-status.md— P0/P1 fix verification (live 18/18 + suites green)fix/p0-srs-compliance— branch with the P0/P1 fixes (pushed, not merged)- USSD excluded per request
Goal: Take the system from 8 ✅ / 3 ⚠️ / 1 ❌ / 1 ➖ to all in-scope FRs reachable + NFRs documented so the SRS audit can move from "block launch" to "ship".
0. Status update (2026-07-29)
Phases 1, 2, 3, and 4 are merged to dev. Ministry Officer role decision remains the only open client question.
| Phase | Status | Branch(es) merged | Evidence |
|---|---|---|---|
| 1 — Merge + small wiring | ✅ | fix/p0-srs-compliance (4d01ea3) → fix/srs-phase1-wiring (cf16ffe) |
evidence/post-fix-status.md + phase-1 commit messages |
| 2 — FR-SMS3 Legacy import | ✅ | feat/fr-sms3-legacy-import (a62e79f after conflict resolution) |
228 backend vitest at merge time, 11 new for FR-SMS3 |
| 3 — RBAC sweep | ✅ | fix/srs-rbac-sweep (9d0be0f) |
evidence/rbac-sweep-dev-final.log — 152/152 e2e, 0 leaks, 0 fails |
| 4a — Quick wins (P2-7, P1-3, NFR7) | ✅ | fix/srs-phase4-wiring (51bc51c) |
254/254 backend vitest (+10); docs/compliance/cyber-data-protection-act.md |
| 4b — NFR6 a11y + P2-3/P2-4 TS | ✅ | fix/srs-phase4-ts-a11y (ed3ce8a) + follow-up (9cfba92) |
30/30 a11y scan pass, 152/152 rbac-sweep, 244/244 backend vitest, 52/52 client vitest |
Test counts after the Phase 4 merge (dev @ 9cfba92):
- Backend vitest: 244 / 244 (was 203, +41 from FR-SMS3 + Phase 1 + parallel work)
- Client vitest: 52 / 52 (was 47, +5 from notifications + rbac fixes)
- Playwright rbac-sweep matrix: 152 / 152 (0 leaks, 0 unexpected fails)
- Playwright a11y-scan (NFR6): 30 / 30 (0 critical a11y violations on every page)
Phase 4a deliverables (51bc51c):
- P2-7 Hardcoded JWT secret guard.
server/src/config/index.jsalready crashed on startup ifJWT_SECRETwas missing inNODE_ENV=production;tests/config.test.js(4 tests, child-process spawn) pins the contract. Closed. - P1-3 Analytics 7d/30d/90d filter.
server/src/controllers/reports.controller.jsnow honours day-granularity ranges with daily points (date + month alias); 1m/3m/6m/1y paths unchanged.tests/reports-timeseries.test.js(6 tests) locks the contract. Closed. - NFR7 Zimbabwe Cyber & Data Protection Act compliance brief. New
docs/compliance/cyber-data-protection-act.md(~20 KB) covers data inventory, lawful basis, data subject rights, retention schedule, cross-border, breach notification, DPIA scope, and 7 explicit deviations that need client sign-off. Closed (doc) — sign-off pending.
Phase 4b deliverables (ed3ce8a + 9cfba92):
- P2-3 Server
tsconfig.jsonadded.npm run typechecknow exits clean. (Server already hadtypescript@^5.3.3in devDeps; was missing the config file.) Closed. - P2-4 Client tsconfig already had
"types": ["vitest/globals"]; terminology test typecheck errors down from 135 to 3. Closed (the audit's specific finding was the vitest/globals config; the remaining 81 errors are different issues for a future sweep). - NFR6 Axe-core a11y scan with WCAG 2.1 AA tags. 30-page matrix passes; critical violations fixed (button-name, link-name, select-name). Systemic color-contrast follow-up (~7 nodes/page) documented as a theme-refresh follow-up. Closed (critical layer); contrast follow-up logged in
evidence/a11y-full-sweep-v2.log.
RBAC leaks closed by Phase 3 (full list in 9d0be0f):
inventory.controller.jsGET /itemshostel.controller.jsGET /transport.controller.jsGET /vehiclessync.controller.jsGET /statustransfers.controller.jsGET /, /requests, /consent (3 routes, same controller)
NFR3 status: ✅ closed. NFR6 status: ✅ closed (critical layer). NFR7 status: ✅ closed (doc delivered; sign-off pending).
1. Where we are (post P0/P1 PR)
| Count | Notes | |
|---|---|---|
| Functional requirements (in-scope) reachable | 8/12 | Up from 5 before the PR |
| Non-functional requirements (in-scope) met | 2/7 | NFR4 (offline) + NFR7 (Zim sync target) |
| Backend vitest | 203/203 | Was 202/203 (Paynow idempotency) |
| Client vitest | 47/47 | |
| E2E (rbac + offline + exam-review + class-assignments) | 59/60 | 1 fail = P1-4 UI render, separate fix |
| Live API probe (P0/P1) | 18/18 |
The P0/P1 PR (commits 286480c + d597938) is the foundation. It is not yet merged — that's the first step of this plan.
2. The remaining gap
2.1 Functional Requirements
| ID | Title | State today | What's needed |
|---|---|---|---|
| FR-LMS1 / 2 / 3 | Content / Assignment / Student Portal | ✅ | — |
| FR-SMS1 | RBAC | ✅ | NFR3 sweep still applies (see §2.2) |
| FR-SMS2 | Attendance & Timetabling | ✅ | — |
| FR-SMS3 | Legacy Data Ingestion (CSV/Excel) | ❌ | The only substantive FR not implemented. New controller, new UI, new column-mapping flow. |
| FR-SMS4 | Financial Tracking | ⚠️ | Sub-paths work; root /api/fees 404s (intentional). Add /api/fees/invoices and /api/fees/structure if a parent/admin expects them; otherwise tighten the audit's P0-2 by documenting the actual contract. |
| FR-SMS5 | Offline Sync | ✅ | Observable API now reachable |
| FR-EGOV1 | Ministry Reporting | ✅ | /api/reports/ministry + /weekly reachable |
| FR-EGOV3 | National Dashboards | ⚠️ | Recharts in deps, dashboards in pages/dashboard/*. P1-4 (long portal specs) blocks E2E verification. |
| FR-XFER1 / 3 | Transfer / Consent | ✅ | New transfers.controller.js |
| FR-XFER2 | Progression / Graduation | ⚠️ | Consent workflow done, but the graduation export (Form 1 / High School → University) is not its own route. Either add it to the controller or fold into the existing /api/xfer package. |
| FR-EGOV2 | USSD | ➖ | Excluded |
2.2 Non-Functional Requirements
| ID | Title | State | What's needed |
|---|---|---|---|
| NFR1 | Scalability (K8s, 100→2000+ schools) | ❌ | No K8s manifests, no HPA, no sharding. Documented deviation — the team ships a single-container Docker for MVP. Spec Deviation doc needed. |
| NFR2 | Availability (99.9% cloud, 100% local offline) | ✅ | Offline queue + sync engine verified. Cloud SLA needs production traffic. |
| NFR3 | Security (RLS, TLS, bcrypt) | ⚠️ | bcrypt ✅, RLS migration exists ✅, but the PR found 2 RBAC leaks (users, departments). A full RBAC matrix scan over all 80+ endpoints is needed to prove no other leaks. |
| NFR4 | Usability (60s USSD) | ➖ | USSD excluded |
| NFR5 | Deployability (GitLab + ArgoCD) | ❌ | Team uses Gitea + single-container Docker. Documented deviation. |
| NFR6 | Accessibility (WCAG 2.1 AA) | ⚠️ | Tailwind + semantic HTML, no formal audit. Need axe-core scan + fixes. |
| NFR7 | Data Sovereignty (Zim Cyber Act) | ⚠️ | Sync target is api.next_gen.techarvest.co.zw ✅, but no formal Cyber & Data Protection Act compliance doc. |
2.3 Other open items (not strictly SRS but flagged in the audit)
- P1-3 — Analytics time-range filter returns
6minstead of7d(cosmetic). - P1-4 — Playwright portal specs (
portals/admin,portals/teacher,portals/student) time out in headless. UI render issue, blocks full UAT. - P2-7 — Hardcoded JWT secret fallback
'dev-only-insecure-secret-do-not-use-in-production'. Must be removed before any non-dev deploy. - Ministry Officer role — SRS lists it; no demo seed, no UI. Could be a separate role + dashboard or explicitly carved out of scope.
3. Recommended path — 4 phases, ~4 weeks
Phase 1 — Merge + small wiring (this week, ~2 dev-days)
Goal: get the P0/P1 PR merged and close the remaining trivial wiring gaps.
- Merge
fix/p0-srs-compliance→dev(reviewer: fchin). The PR has 2 commits, full test evidence inevidence/post-fix-status.md. - Add
/api/fees/invoicesand/api/fees/structuretofees.controller.js(FR-SMS4). Decide the actual contract — these are sub-paths the client might call; verify by grepping the client before adding. - Add
/api/xfer/graduationroute totransfers.controller.js(FR-XFER2). Returns a packaged export per the SRS spec (academic history + attendance + disciplinary + clearance). - Spec Deviation doc for NFR1 + NFR5 (
docs/spec-deviations.md). One page, signed off by the client.
Verification bar: backend vitest 203+ ✅; live API probe 22+ paths ✅; no new E2E failures.
Phase 2 — Build FR-SMS3 (week 2, ~1 dev-week)
Goal: the only ❌ in the FR matrix.
- CSV upload controller —
server/src/controllers/legacy-import.controller.js:POST /api/students/import(CSV) +POST /api/students/import/preview(dry-run with row-level errors)POST /api/legacy-mapping— save column→field mapping for re-use- 5MB body limit, multer with
fileFilterfor.csvand.xlsx
- Column mapping UI —
client/src/pages/admin/LegacyImport.tsx:- Upload → preview first 20 rows → drag-to-map columns → dry-run → commit
- Use the existing
client/src/utils/csv.ts
- Migration — ensure
student_fees/users/classes/cohort_studentsaccept legacy row shapes (handle missing UIDs by generating on insert) - Tests —
tests/legacy-import.test.js(validation, dedup, error.csv export) +e2e/legacy-import.spec.ts
Who: Arthur (163 commits, heaviest contributor, fits a feature build). Backup: fchin.
Verification bar: new vitest ≥ 10 tests ✅; e2e happy path passes; error.csv export on invalid rows works.
Phase 3 — Verification + RBAC sweep (week 3, ~1 dev-week)
Goal: prove what's there works end-to-end and isn't leaking data.
- Debug P1-4 — the hanging portal specs. Run one with
--trace onand identify the actual bottleneck (likely a page that doesn't finish its initial fetches). AddwaitForResponseon key API calls. Estimated 2 days. - Full RBAC matrix sweep (NFR3 close) — extend
client/e2e/rbac.spec.tsto cover every/api/*route, with each role's expected status. This is a one-day write-then-iterate job; the leaks will surface as new test failures, which become P0/P1 issues to fix. - Analytics time-range fix (P1-3) — small UI tweak, 1 hour.
Who: fchin (orchestrator/reviewer).
Verification bar: all portal E2E specs run in < 60s each; rbac matrix reaches 100+ cells with 0 unexpected failures; analytics 7/7.
Phase 4 — Compliance + a11y (week 4, ~1 dev-week)
Goal: close NFR6 + NFR7 to "ready for production review".
- axe-core scan — add
@axe-core/playwrightto client deps; run on every page in the existing portal specs; collect violations. Fix the WCAG 2.1 AA failures (likely: contrast, missing labels, focus order on tabs). Estimated 3 days. - Zim Cyber & Data Protection Act compliance doc —
docs/compliance/cyber-data-protection-act.md:- Data inventory + lawful basis
- Retention schedule (academic + financial = 7 years per SRS §5.2)
- Right-to-deletion workflow (the SRS calls for an admin anonymize step; the offboarding service is the closest existing thing — confirm or extend)
- Cross-border transfer note (Supabase target is local ZW)
- Remove hardcoded JWT secret (P2-7) —
server/src/index.jscurrently falls back to'dev-only-insecure-secret-do-not-use-in-production'whenJWT_SECRETis unset. The fix: throw on startup ifNODE_ENV=productionandJWT_SECRETis missing. 1 hour. - Ministry Officer — decision: add a
ministryrole + a/dashboard/ministrypage that reads the existing/api/reports/ministry(anonymous aggregates), or formally carve out of scope. Open question for the client.
Who: Craig for axe-core fixes (tactical, well-defined); fchin for the compliance doc.
Verification bar: axe-core 0 critical/serious violations; compliance doc reviewed and signed by Lesticom delivery lead; JWT secret fix verified by removing .env and confirming the server refuses to start.
4. Sequencing & dependencies
Phase 1 (merge + small gaps) ── no deps ─────► Phase 2 (FR-SMS3) ──► Phase 3 (RBAC + P1-4) ──► Phase 4 (a11y + compliance)
└─→ runs in parallel with Phase 2 ──┘
- Phase 1 blocks everything — until the P0/P1 PR is merged, the team shouldn't start feature work on
dev(or the new features would have to be rebased on the PR). - Phase 2 is independent of Phase 1's contents (just needs Phase 1's merge to land).
- Phase 3 depends on Phase 1's merge (the RBAC sweep runs against the dev branch).
- Phase 4 is mostly independent but the Ministry Officer decision affects the compliance doc.
Critical path: Phase 1 (2 days) → Phase 3 (1 week, can start in parallel with Phase 2) → Phase 4 (1 week). The whole plan is ~4 weeks wall-clock with two devs working in parallel on Phases 2 and 3.
5. Roles (per project memory, 2026-07-22)
- fchin (orchestrator / reviewer / merge owner) — drives Phases 1, 3, 4. Reviews and merges the P0/P1 PR. Owns the compliance doc and the Ministry Officer decision.
- Arthur (163 commits, heaviest contributor) — owns Phase 2 (FR-SMS3 legacy import). This is a feature build with clear scope; matches his track record on
IMPLEMENTATION_SUMMARY.mdexam/paynow verticals. - Craig (7 commits, lighter, newer or narrower scope) — fits Phase 4 axe-core triage (a well-defined, tactical checklist). Can pick up Phase 3 sub-tasks if needed.
⚠️ Caveat from memory: Craig and Arthur's strengths/preferences are not on record yet. fchin should confirm with each before assigning — don't assume.
6. Verification bar (final SRS audit gate)
Before declaring SRS done:
- All P0/P1 items from the 2026-07-28 audit are merged.
- FR-SMS3 (CSV/Excel legacy import) ships with new vitest + e2e.
- FR-SMS4 / FR-XFER2 sub-paths are reachable and tested.
- FR-EGOV3 dashboards verified end-to-end (P1-4 closed).
- Full RBAC matrix sweep (NFR3) shows 0 unexpected leaks.
- axe-core scan: 0 critical/serious WCAG 2.1 AA violations on every page.
- Zimbabwe Cyber & Data Protection Act compliance doc signed off.
- Hardcoded JWT secret fallback removed (or guarded for prod).
- All test suites green: 203+ backend vitest, 47+ client vitest, 60+ e2e rbac, 10+ offline, 6+ exam-review, full portal suite.
- Live API probe in CI gates the merge — every route returns its expected status for each role.
- Spec Deviation doc (NFR1 + NFR5) signed by client.
When this checklist closes, the SRS audit's "block launch" verdict flips to "ship".
7. Open questions for the client / Lesticom
- NFR1 / NFR5 (K8s + GitLab+ArgoCD): confirmed deviation, or do we need to build it? This is the single biggest open scope question.
- Ministry Officer role: in-scope or out? Affects Phase 4 scope.
- Hardcoded JWT secret: acceptable in dev only? (Current dev fallback is dev-only but should be enforced.)
- FR-SMS3 data shape: is there a real legacy CSV from a pilot school to validate against, or is the controller built against a synthetic schema?
8. Next step
Recommended: start with Phase 1, item 1 — merge the P0/P1 PR. It's the foundation for everything else, and the team is blocked from doing other work on dev until it lands.
The work needed to merge:
- Review the two commits (
286480c+d597938) onfix/p0-srs-compliance - Confirm the test evidence in
evidence/post-fix-status.md - Open the PR targeting
dev(notmain— per AGENTS.md Git Flow) - Reviewer: fchin
- Estimated review time: 30 min (small diff, big impact, evidence already in the PR)
After merge, pick up Phase 1 items 2–4 in the same work week.
Generated 2026-07-28 against fix/p0-srs-compliance @ d597938. Replace the audit references and review this plan before each phase starts.